PROJECT SCHEDULE

The following is a summary of key tasks and meetings that have been completed in association with the preparation of a multi-jurisdictional Integrated Solid Waste Management (ISWM) Plan to address solid waste issues in Sublette, Lincoln, Uinta, and Teton Counties for the next 20 years.

August 1, 2007 Letter of Intent – Provide notification that Sublette, Teton, Lincoln, and Uinta County Commissions passed resolutions in support of preparing a multi-jurisdictional ISWM Plan.
   
August 14, 2007 Project Kick-Off Meeting – Review solid waste issues in Wyoming, the ISWM planning process, the roles and responsibilities of the planning partners and stakeholders, public outreach strategies, and preliminary planning issues/objectives. 9 AM to 3 PM at the Sublette County Library, Pinedale.
   
January 2008 Local Planning Meetings – Review local planning issues and identify a list of reasonable alternatives for consideration by the regional planning group.

January 14, 1 PM to 5 PM at the Uinta County Library, Evanston
January 15, 1 PM to 5 PM at the Lincoln County Courthouse, Kemmerer
January 17, 8 AM to 12 PM at the Teton County Administration, Jackson
January 18, 8 AM to 12 PM at the Sublette County Library, Pinedale
   
March 27, 2008 Regional Planning Meeting – Review profiles of existing systems and local planning issues, and identify a short list of regional alternatives for detailed analysis. 9 AM to 4 PM at the Lincoln County Library, Kemmerer.
   
August-September 2008 Regional Planning Meeting – Review preliminary Report of Economic Analysis of Alternatives. Meeting time and location have not yet been identified.
   
October 1, 2008 Report of Economic Analysis of Alternatives – Submit report to the Wyoming Department of Environmental Quality.
   
November-December 2008 Regional Planning Meeting – Review preliminary draft ISWM Plan. Meeting time and location have not yet been identified.
   
January 2009 Public Comment Period – Solicit comments on the preliminary draft ISWM Plan.
   
February 2009 Regional Planning Meeting – Review public comments, select a preferred alternative, and identify implementation strategy. Meeting time and location have not yet been identified.
   
March-April 2009 Regional Planning Meeting – Review preliminary Draft ISWM. Meeting time and location have not yet been identified.
   
May 1, 2009 Draft ISWM Plan - Submit report to the Wyoming Department of Environmental Quality.
   
May-June 2009 Regional Planning Meeting – Address Wyoming Department of Environmental Quality comments on Draft ISWM Plan. Meeting time and location have not yet been identified.
   
July 1, 2009 Final ISWM Plan - Submit report to the Wyoming Department of Environmental Quality.
   